Detach & reinstall · Stateline · 2026

Panels off Wednesday. Back on Monday. It rained for two of those days.

Rails and conduit set on a roof mid-way through a solar reinstall

The job

The job
Array12 modules on a metal-roofed outbuilding
WorkFull detach, storage on site, reinstall
Hardware100% new rails, clamps and attachment hardware
Cost$275 per panel each way, $6,600 total
System offline5 days

How the week ran

How the week ran
DayWhat happened
WednesdayBraven detached the array, isolated the system, inventoried and stored the hardware on site
ThursdayRain. No roof work possible
FridayRain. No roof work possible
SaturdayRoofer completed the roof
MondayBraven reinstalled, re-commissioned, confirmed production

Why this is the number that matters

Two of the five days were rained out and the schedule still held. That is the difference between a solar sub who blocks your job and one who doesn't.

The homeowner's system was offline for five days and producing again on the Monday. Nobody was waiting on us, the roofer was not standing in a driveway, and the array went back on new hardware rather than the weathered clamps that came off it.

We schedule detach and reinstall inside a one-week window of the roof work because weather does this. Planning for a perfect week is how a two-day delay becomes a three-week delay.

What went back on the roof

All-new rails, clamps and attachment hardware. We do not reuse racking that has been through one removal. Every mounting point carries our twelve-year workmanship warranty against leaks.

Roof work coming up?

Send the panel count, the roof deadline and the roofer's name if you have one. We come off before they start and back on after they finish.

Or call(815) 443-3155Monday to Friday, 8am to 5pm

Tell us what you need

Call (815) 443-3155Get a Quote